Kinder Morgan - Permian Highway Project

Project consists of 425 miles of 42 inch pipe. We procured and prepared all the pipe yards and rail sidings and were also tasked with Unloading, Hauling and Racking all the pipe.

Denbury CCA Development

Spanning across 3 States this project is 127 miles of 12 and 16 inch pipe that we loaded, hauled and stockpiled in pipeyards procured and prepared by Dun Transportation.

Enterprise Products - M2E3

Started September 2019, this project consisted of 300 miles of 30 inch pipe. Dun procured multiple pipe yards, rail sidings, and prepared them. We also unloaded, hauled, and stockpiled all pipe on this project.